Minooka Data Center WatchMinooka & Surrounding Area — Public Resource

CyrusOne Data Center Campus, Yorkville

Northeast corner of Eldamain Road and Faxon Road, Bristol Township — Yorkville, IL (Kendall County)

Approved

Summary

CyrusOne, a Dallas-based data center developer, received unanimous approval from the Yorkville City Council on July 9, 2024 — becoming the first data center project approved in Yorkville's Eldamain Corridor. The campus spans 228 acres at the northeast corner of Eldamain Road and Faxon Road.

Originally planned as nine two-story buildings totaling 2.4 million square feet, the project was revised in early 2026 to eight buildings (2.1 million sq ft) with a substantially smaller electrical substation; further amendments to reduce all buildings from two-story to one-story are anticipated.

CyrusOne fronted over $10 million in water and sewer infrastructure costs, which the city will reimburse via utility tax revenue over time. Construction began in Q1 2026, with power delivery targeted for 2027.

Key Facts

Data Center Buildings

8 buildings (amended from 9); 2.1 million sq ft (down from 2.4M)

Total Site

228 acres in Bristol Township

Electrical Substation

1 on-site substation — originally 800,000 sq ft; halved in 2026 amendment

Stormwater Infrastructure

6 on-site stormwater basins

Estimated Annual Tax Revenue

~$1 million per building; ~$9 million total at full build-out

Tax Rebate Structure

First $1M in utility taxes rebated at 50%; next $8M rebated at 60%

Infrastructure Investment

CyrusOne fronted $10M+ in water/sewer; reimbursed via tax revenue over time

Construction Start

Q1 2026

Power Delivery Target

2027

Build-Out Timeline

Phases over 10–20 years

Related Project

CyrusOne & Green Door Capital — separate 128-acre plan north of Faxon Rd, south of Corneils Rd, east of Beecher Rd

* Projected figures from Village of Minooka fact sheet.

Timeline of Events

  1. February 10, 2026

    Plan amendment presented at City Council: reduced to 8 buildings, substation halved

    United City of Yorkville City Council

    Developer representative Russ Whitaker presented revised plans on behalf of CyrusOne, reducing the campus from 9 to 8 buildings (2.4M to 2.1M sq ft) and halving the substation from its original 800,000 sq ft footprint. Whitaker said construction would begin Q1 2026, transformer delivery and installation would occur later in 2026, and power delivery is expected in 2027. Further amendments to convert all eight remaining buildings from two-story to one-story are anticipated; Whitaker stated this height reduction 'should not change the amount of power used for the overall project.'

  2. July 9, 2024

    City Council unanimously approves development and infrastructure agreements

    United City of Yorkville City Council

    Unanimous council approval of the development agreement and infrastructure cost-sharing arrangement. CyrusOne agreed to front costs for road improvements and water/sewer infrastructure extension to the site; the city will reimburse CyrusOne for utility infrastructure via tax revenue over time. The city and CyrusOne also agreed to a 50/50 cost-sharing split on utility construction costs and power pole relocation if required during future road reconstruction.

  3. Prior to July 9, 2024

    Planning & Zoning Commission unanimous approval

    Yorkville Planning & Zoning Commission

    P&Z Commission unanimously recommended approval of the Planned Unit Development in M-2 General Manufacturing District prior to the full council vote.

How Officials Voted

OfficialTitleVoteDateMeeting
City Council (all members)Yorkville City CouncilUnanimous YesJuly 9, 2024Yorkville City Council — CyrusOne development agreement approval

Incentive Agreements

Utility Tax RebateApproved: July 9, 2024

First $1 million in annual utility taxes rebated to CyrusOne at 50%; next $8 million rebated at 60%

Approved by: City of Yorkville

Infrastructure Cost ReimbursementApproved: July 9, 2024

CyrusOne fronted $10M+ for water and sewer infrastructure extension to the site; city to reimburse via utility tax revenue over time

Approved by: City of Yorkville

Documents Library

DocumentTypeDateSourceLink

Resources & Coverage

Sort:
NewsShaw Local / Kendall County Now· February 12, 2026
First-Approved Data Center in Yorkville Downsizing Plans, All Buildings Likely to Be Half the Height

Reports CyrusOne's revised plans presented at the Feb. 10, 2026 City Council meeting: reduced from 9 to 8 buildings (2.4M to 2.1M sq ft), substation halved from its original 800,000 sq ft. Russ Whitaker confirmed construction begins Q1 2026, transformer delivery later in 2026, power delivery in 2027, and further height reductions (two-story to one-story) are anticipated. Also discloses a separate 128-acre CyrusOne/Green Door Capital project north of Faxon Rd, south of Corneils Rd, east of Beecher Rd. Notes Yorkville's Eldamain Corridor has approximately 3,000 acres under data center development.

NewsShaw Local / Kendall County Now· July 15, 2024
Yorkville City Council Approves Plan for 228-Acre Data Center Campus

Covers the unanimous July 9 approval of CyrusOne's 228-acre campus at Eldamain and Faxon roads. Details the nine two-story building plan, single electrical substation, six stormwater basins, estimated $1M per building in annual tax revenue ($9M total), tax rebate structure (50%/60%), and $10M+ infrastructure fronted by CyrusOne.

NewsWSPY News· July 2024
Yorkville City Council Approves Development Agreement with CyrusOne for Data Center

Reports unanimous City Council approval of the CyrusOne development agreement on July 9, 2024. Notes CyrusOne is fronting road improvement and utility infrastructure costs, with the city reimbursing via tax revenue; 50/50 cost-sharing on utility construction and power pole relocation.

NewsData Center Dynamics· 2024
Yorkville City Council Approves CyrusOne Data Center Development in Illinois

Data Center Dynamics coverage of the Yorkville City Council's approval of the CyrusOne data center development.